【Daily Question】Utilities – Civil Engineering – 20190606

2019-06-06View Original

Thread Content

A construction company has a 3-month deadline for this project; work began on May 1, 2002. The planned amounts of work to be completed in May, June, and July are 500 tons, 2,000 tons, and 1,500 tons respectively, with a planned unit price of 5,000 yuan per ton; The actual volumes of work completed were 400 tons, 1,600 tons, and 2,000 tons respectively, and the actual price throughout May to July was 4,000 yuan per ton. Then the investment deviation at the end of June is ( ) ten thousand yuan. A.450 B.-450 C.-200 D.200 Answer: C

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.