【Daily Question】Utilities - Mechanical & Electrical - 20191209
Thread Content
According to the “General Specifications for Construction and Acceptance of Mechanical Equipment Installation Engineering”, which of the following statements regarding the supervision work during the construction preparation phase are correct? ( ) A. Verification of construction conditions, including checking whether construction drawings and equipment technical documents are complete and valid.B. For medium- to large-scale, special, or complex installation projects, it is essential to verify whether the construction contractor has prepared a construction organization design or construction plan, and whether such design/plan has been approved.
C. If the building structure needs to be utilized as a load-bearing point for lifting or handling equipment during installation, the structural load-bearing capacity must be calculated; in necessary cases, approval from the design unit is required before such use is permitted.
D. The location, geometric dimensions, and quality requirements of equipment foundations must comply with the provisions of the current standard “Code for Construction and Acceptance of Reinforced Concrete Works”. There must also be relevant acceptance documentation or records.
E. In case of any abnormal geological conditions encountered during foundation construction, the construction unit must be promptly informed. Foundation construction should then be suspended until the construction unit provides instructions on how to proceed.
Answer: ABCD
B. For medium- to large-scale, special, or complex installation projects, it is essential to verify whether the construction contractor has prepared a construction organization design or construction plan, and whether such design/plan has been approved.
C. If the building structure needs to be utilized as a load-bearing point for lifting or handling equipment during installation, its load-bearing capacity must be calculated; under such circumstances, permission from the design unit must be obtained prior to use.
D. The location, geometric dimensions, and quality requirements of equipment foundations must comply with the provisions of the current standard “Code for Construction and Acceptance of Reinforced Concrete Works”; relevant acceptance documentation or records must also be available.
E. In case of any abnormal geological conditions encountered during foundation construction, the construction entity must be promptly informed. Construction activities should then be suspended until the construction entity provides instructions on how to proceed