What are the construction sequence steps for installing light well points? We welcome active participation in discussions; the system offers generous rewards for answering questions from VIP members! ! !
Reply #22020-09-13
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #32020-09-13
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #42020-09-13
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #52020-09-13
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #62020-09-13
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #72020-09-14
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #82020-09-14
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #92020-09-19
①Trench for well drilling; ②Lay the main water collection pipe ; ③punching ; ④Install wellpoint pipes ; ⑤Filled sand filter media ; ⑥Connect the well point pipes to the main collector pipe using elbow connectors ; ⑦Install pumping equipment and conduct a test pump
Reply #102020-09-21
Surveying and setting out, digging ditches at the well sites, drilling holes, installing water suction wells, filling with coarse sand filter media, laying collection pipes, connecting the collection pipes to the well pipes, installing pumping equipment, conducting trial pumping, starting actual pumping, carrying out foundation construction, removing the well pipes

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.