This post was last edited by Juan Combantou at 2019-5-5 16:30. The DN5000 vertical atmospheric pressure cone-top storage tank has no connecting pipe on the top of the cone. How to design the cone-top structure? Is the structure designed as shown in Figure 1 easy to process and manufacture? Previous predecessors were all designed in the form shown in Figure 2, with an angle steel ring on the top. Figure 1 Figure 2
You can leave a hole and then use a round flat plate to overlap and weld it.
Why do we need to leave a hole? Is it because the center of the cone top is difficult to process?
What the poster means is that after the cone top is unloaded and assembled, if there is a connecting tube at the cone tip, a hole can be reserved to facilitate the unloading and unfolding. Now that the nozzle is gone, the tip of the cone needs to be sealed.
Yes, what I mean is that if the cone top is pointed, will it be easier to process? Is it necessary to leave a hole when blanking and then fill the tip after molding?
I feel that the small diameter is easier to process. Large diameter ones are inconvenient. You can leave a round hole like a vault. Then take a slightly curved circular plate and fasten it.
This post was last edited by wanlirn on 2019-5-7 13:15. There are about 1,000 flat plates in the middle of the editor. The sharp ones are too ugly to use for work and insulation. There is a flat one in the middle. You can stand and look at the scenery in the distance hahaha.