Questions regarding welding issues after internal inspection of the boiler

2023-03-05View Original

Thread Content

My boiler is now ready for an internal inspection. There are two types of pipes to be cut for endoscopic examination: 12Cr1MoV pipes with dimensions of 60*6 mm, and 20G pipes with dimensions of 32*4 mm. I would like to know whether heat treatment is required for both types of pipes after welding. Are there any standards specifying which materials used in boilers, along with their corresponding specifications, require heat treatment and flaw detection after welding? Thank you in advance for your assistance
Reply #22023-03-06
I wonder what this endoscopy can reveal – crystals, scale buildup? ? ? For such a pipe diameter, if it is inserted into an endoscope through an opening, the required diameter of that opening is likely to be not very large; it can simply be welded shut after use. For reference.
Reply #32023-03-06
12Cr1MoV requires heat treatment

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.