The owner enters into a design contract with the design institute; according to the unified design regulations, the design institute is required to prepare a project design commencement report. What is the content of this report? Can it be sent to the owner? Is it still an internal report of the design institute?
You may refer to whether separate start-up reports are required for the feasibility study, preliminary design, and detailed design of the same project: https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=884976&shareuid=301199
A work report on the initiation of project design within the design institute is usually not necessary to provide to the client. The main contents of the design commencement report are as follows: 1. Project overview: Project summary (project name, scale, product specifications, site overview, etc.), project scope, contract type, issues requiring special attention (including the owner’s specific requirements) ; 2. Contents of the start-up report: Project organization structure (including a list of key team members), project work breakdown structure (PSWBS), procedures for communication and coordination with the client, procedures for coordination with subcontractors, internal coordination within the company, project schedule, requirements for spare parts, requirements regarding design documents and drawings, items to be reviewed and approved by the client, language and units of measurement to be used in project documents, confidentiality and safety precautions, and uniform regulations for engineering projects ; 3. Key points for project implementation: Design key points (design scope, degree of automation, capacity margin of the installation, special requirements, etc.), requirements for design schedule management and control, requirements for design quality management and control, requirements for project cost control, requirements for project material management and control, requirements for comprehensive project inspection and control, reporting system ; 4. Project design schedule: Collecting basic design information, holding the project kickoff meeting, formulating unified project specifications, initiating and completing the design phase (including conceptual or preliminary design, as well as detailed design or construction drawings), and preparing a control estimate ; 5. Procedures for coordinating with the owner.
Owners can learn about the relevant contents of the \"Project Kick-off Report\" by attending the project kick-off meeting held by the design institute.
Prepare the project commencement report based on the work contents and scope specified in the design contract. Simply put, make up whatever the contract tells you to do.
Since projects designed by design institutes usually have standards. You can simply ask the owner, and then download a set of the necessary documents from the internet according to the standards (there are many forms available, such as start-up reports, completion reports, and so on).