Welded joint heat treatment

2022-07-14View Original

Thread Content

What does it mean in 150.4 that for carbon steel, the values are greater than 32 and greater than 38 (with a preheating of 100°C before welding)? Does this mean that heat treatment is not necessary after preheating, or is it required to preheat first for materials with a value greater than 38 before undergoing heat treatment? Can anyone explain this?
Reply #22022-07-14
Both pre-welding heating and post-weld heat treatment serve the purpose of improving the quality of the weld, but they are distinct processes; in most cases, both need to be carried out!
Reply #32022-07-14
Different requirements apply depending on the material; preheating is necessary before welding, while post-weld treatment is required after welding – it is not necessary for all materials, and it depends on the relevant specifications
Reply #42022-07-15
No preheating before welding; heat treatment after welding is required for thicknesses greater than 32 mm; Preheating is required before welding; heat treatment after welding is necessary for thicknesses greater than 38 mm.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.