This post was last edited by yuchenchf on 2017-1-7 at 17:43. Reward for participation: 2 wealth points. Correct reward: 9 Wealth. A contract project received its completion certificate at the beginning of November in a certain year. Two weeks later, the contractor submitted a final settlement request, indicating that there was still one cost overage claim that needed to be addressed within 28 days, in late October. In this situation, the contractor ( ). A. A claim can be made, as the incident occurred within 28 days. B. A claim can be made, as the project has not yet received the final settlement certificate. C. No claim can be made, as this incident took place before the project acceptance certificate was issued. D. No claim can be made, as this incident occurred after the final settlement certificate was received. C
C. No claim can be made, as this incident occurred before the acceptance certificate for the work was issued
C. No claim can be made, as this incident occurred before the acceptance certificate for the work was issued
C. No claim can be made, as this incident occurred before the acceptance certificate for the work was issued
A contract project received its project acceptance certificate at the beginning of November in a certain year. Two weeks later, the contractor submitted a final settlement request, indicating that there was still one cost overrun claim from late October that needed to be addressed within 28 days; in this case, the contractor ( C ). A. A claim can be made, as the incident occurred within 28 days. B. A claim can be made, as the project has not yet received the final settlement certificate. C. No claim can be made, as this incident happened before the project acceptance certificate was issued. D. No claim can be made, as this incident occurred after the final settlement certificate was received