How should pressure testing and purging be carried out after the low-pressure steam pipeline is installed? ? Are there any regulations?

2018-12-16View Original

Thread Content

How should pressure testing and purging be carried out after the low-pressure steam pipeline is installed? ? Are there any regulations?
Reply #22018-12-16
GB50235-2010: Code for Construction and Acceptance of Industrial Metal Piping Projects; GB50184-2011: Code for Quality Inspection and Acceptance of Industrial Metal Piping Projects. Send something as a token
Reply #32018-12-16
How do you pressure test and purge your steam pipelines?
Reply #42018-12-16
Direct steam purging is sufficient; if the pressure is low, vent it at the break point, and if the pressure is high, use pipes to direct it outside for discharge

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.