Steps for putting the flowmeter into use

2019-03-01View Original

Thread Content

For flow meters that are newly installed or put into operation after pipeline maintenance, they should be commissioned in the order of (first opening the bypass valve, then the valve upstream of the flow meter, followed by the valve downstream of the flow meter, and finally gradually closing the bypass valve). May I ask everyone: why is it necessary to open the valve upstream of the flow meter first, and then the valve downstream of it?
Reply #22019-03-02
To ensure that the material completely fills the flow meter, accurate measurements can be obtained by the flow meter. If the downstream valve is opened first, the material may not fill the flow meter
Reply #32019-03-02
This is also the case for split-flow meters; in rotor flow meters, it is usually necessary to open the downstream side first, to avoid excessive impact on the float that could cause jamming
Reply #42019-03-02
Before asking this question, you can try it on the device. You’ll know right away which one to use! :)
Reply #52019-03-06
This is the **professional assessment question bank’s
Reply #62019-03-14
Opening the upstream valve first and then the downstream valve is to prevent the pipeline from being empty. Open the downstream valve first; once the medium flows away, the pipe will be empty.
Reply #72019-03-19
The newly installed electromagnetic flowmeter doesn’t have a bypass, and my measurements aren’t accurate right now. What’s the reason for this?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.