I would like to know how many small sewage treatment units are needed in a factory; since there are no buildings or tanks, what procedures are required, and is a construction permit necessary?

2019-09-04View Original

Thread Content

I would like to ask: If the factory adds a few more wastewater treatment units on top of its existing facilities, without constructing any buildings or tanks, what procedures are required? Is a construction permit necessary?
Reply #22019-09-05
Wastewater treatment equipment? If there are no regulated categories, it can be purchased and installed directly.
Reply #32019-09-05
No need to report? A construction permit?
Reply #42019-09-05
If there are no significant changes to the wastewater treatment processes, the company’s internal process change procedure can be followed; As a precaution, it is recommended to consult the local environmental protection authorities regarding the construction procedures. Thank you!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.