For a pressure vessel at normal pressure that contains Class A flammable materials, are there any special procedures required for such a vessel?

2019-09-18View Original

Thread Content

The pressure vessel has a capacity of 10 cubic meters and is used to hold Class A flammable material (dichloroethane). Are there any special procedures required for this vessel? Are there any special requirements for container inspection and pressure testing? Is it necessary to inspect and pressure-test it as a pressure vessel?
Reply #22019-09-18
The boiling point of dichloroethane is 83–84°C, with a saturated vapor pressure of 13.33 kPa at 29.4°C. According to the \"Design Code for Storage Tanks in Petrochemical Storage and Transportation Systems\" SH/T 3007-2014, section 4.2.5, for storing liquids of categories A and B whose boiling point is 45°C or higher, or whose saturated vapor pressure is not greater than 88 kPa at 37.8°C, floating roof tanks or internal floating roof tanks should be used. For other liquid chemical products of Class A-B and Class B-A that require special storage conditions, fixed-roof storage tanks, low-pressure storage tanks, or horizontal storage tanks with a capacity of 100 m3 or less can be used; however, one of the following measures must be taken: install a nitrogen or other inert gas sealing system to capture and handle the gases released from the tank, or install a nitrogen or other inert gas sealing system to keep the storage temperature 5 °C or lower than the liquid’s flash point. Dichloroethane can be stored in atmospheric or low-pressure storage tanks such as fixed-roof tanks, low-pressure tanks, and horizontal tanks with a capacity of 100 m3 or less; however, a nitrogen or other inert gas sealing system must be installed. Atmospheric or low-pressure tanks are not subject to the regulations applicable to pressure vessels.
Reply #32019-09-20
What about pressure testing after manufacturing? Is just a water retention leak test sufficient?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.