What tasks are required as the person in charge of instrumentation for a new project?

2020-04-26View Original

Thread Content

It has been determined that the EPC model will be used; what issues need to be discussed with the automation equipment manufacturer? Please, guys, give me some help. Thank you.
Reply #22020-04-26
First, learn the drawings well on your own, familiarize yourself with the acceptance criteria, and read the technical attachments of the EPC contract carefully. Understand the hardware system being used (training can generally be requested if you are not familiar with it). What are the items included in the factory testing for equipment? Construction and commissioning schedule
Reply #32020-04-26
Bro, thanks first, but maybe I didn’t explain clearly – for the instrumentation side, we plan to use EPC, and the bidding process hasn’t started yet. I just want to ask what information needs to be mastered based on this standard, and what aspects and information need to be discussed with the self-control company.
Reply #42020-04-26
Formulate selection principles for control instruments (a framework for guidance), participate in instrument selection, be involved in supplier recommendation and evaluation, take part in technical discussions, attend the technical evaluations for procurement purposes to determine the instrument suppliers, participate in FAT, and engage in reviews during the design phase.
Reply #52020-04-26
We are still in the bidding preparation phase; my role is mainly to discuss the scope of the bidding, the delivery timeline, the construction methods, as well as the key challenges and difficulties involved. I’m not sure if there’s anything missing or that requires special attention. The contract we have signed with the design institute is relatively small-scale; it only provides the \"Process Flow Diagram,\" \"Equipment Layout Diagram,\" and \"Cable Tray Layout Diagram.\" Other documents such as the \"Instrument List\" and \"Instrument Layout Diagram\" need to be redesigned by the automation company. I’ve worked on a small workshop project before, but back then the design drawings were already complete, and it wasn’t an EPC model – the situation was quite different from this time. So I’d like to know what to do in this case.
Reply #62020-04-26
We are still in the bidding preparation phase; my role is mainly to discuss the scope of the bidding, the delivery timeline, the construction methods, as well as the key challenges and difficulties involved. I’m not sure if there’s anything missing or that requires special attention. The contract we have signed with the design institute is relatively small-scale; it only provides the \"Process Flow Diagram,\" \"Equipment Layout Diagram,\" and \"Cable Tray Layout Diagram.\" Other documents such as the \"Instrument List\" and \"Instrument Layout Diagram\" need to be redesigned by the automation company. I’ve worked on a small workshop project before, but back then the design drawings were already complete, and it wasn’t an EPC model – the situation was quite different from this time. So I’d like to know what to do in this case.
Reply #72020-04-26
Since the EPC turnkey approach is adopted, aspects such as the scope of the bidding, delivery timeline, and methods of construction are not something you need to focus on – these are the responsibilities and obligations of the EPC contractor. All you need to do is translate all of your company’s legitimate requirements into contractual terms and include them within the scope of the EPC contract.
Reply #82020-04-26
At this stage, you should state your requirements and prepare a list; for some instruments, on-site measurement and control may be necessary

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.