Is it necessary to consult the design institute for any changes to the interlocks in a DCS system?

2022-03-28View Original

Thread Content

Could risk discussions be held within the company to identify the risks associated with changes, and then decide on whether a change is necessary or not?
Reply #22022-03-29
Sure, as long as you can take on the responsibility. In fact, the workshop often makes adjustments to certain interlocks that interfere with operation.
Reply #32022-03-29
The DCS interlock can be changed whenever you want: lol
Reply #42022-03-29
This post was last edited by feng*aosa on 2022-6-3 at 16:52. Changes to system interlocks are carried out in accordance with the unit’s management regulations; it is up to those regulations to decide whether to consult the design institute.
Reply #52022-03-29
Sure. It is also possible to entrust a design institute to participate as well
Reply #62022-03-30
No matter how reasonable the interlock changes may be, the design institute generally will not approve your modifications. There is no benefit to him at all; instead, he faces the risk of having to take responsibility. So, generally it’s discussed within the company, and then **the junior manager signs off before proceeding with it.
Reply #72022-05-27
Interlock changes are mainly due to process-related reasons. After the facility is built and put into operation, such changes are decided through discussions among the company’s internal production operations, process, and instrumentation teams; they have little to do with the design institute
Reply #82022-05-27
Unless the process package is a process designed that way
Reply #92022-05-29
Not necessarily, but the reasons for the change must have thorough analysis and supporting evidence
Reply #102022-05-29
Internal discussions lead to the creation of an interlock change order, which is then forwarded for archiving
Reply #112022-05-31
It’s sufficient to keep proper change records and conduct analyses within one’s own company; there is no need to consult a design institute.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.