Questions regarding the quality supervision station

2017-08-02View Original

Thread Content

We are a private petrochemical company planning to install new equipment. Is it necessary to hire a quality supervision agency? Is this service free or does it incur costs? Thank you!
Reply #22017-08-03
Regardless of the type of your enterprise, whenever you undertake a project, you must go to the relevant desks at the local government service center to complete various registrations such as those with the quality supervision and safety supervision authorities. The work of the Quality Supervision Station involves carrying out **functions, and no payment is required.
Reply #32017-08-03
Without passing the quality inspection, it is not possible to carry out completion acceptance later on, and normal production cannot commence
Reply #42017-08-10
The quality supervision station is part of the Housing and Urban-Rural Development Commission system; your facility must include an industrial plant; The construction of these factories requires the involvement of a quality supervision agency ; Procedures must be initiated from the planning stage; once the construction permit is obtained and work begins, the quality supervision station will start to conduct inspections.
Reply #52017-09-02
Another question: Is supervision by a quality inspection agency required for installation work (including equipment and pipeline installation)? Thank you.
Reply #62017-09-03
If pressure pipelines or special equipment are involved, it is necessary to submit a report to the Special Equipment Inspection Institute of the Technical Supervision Bureau (Boiler Inspection Institute) for supervision.
Reply #72018-01-31
The quality inspection station is only responsible for infrastructure projects; they do not oversee installation projects; There is generally no management department. If there are special equipment and pressure pipelines, etc., it is necessary to go to the special equipment management department of the Technical Supervision Bureau to complete procedures such as installation notification.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.