[Engineering Version] Daily Question 20180109

2018-01-09View Original

Thread Content

Among the following options, which statements regarding the general construction layout plan are correct? (  )   A. Large quantities of materials, finished products, semi-finished products, and machinery and equipment shall not be stored in such a way as to occupy the roads within the site or other safety facilities.
B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery should be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily.
Correct answers: ACE
Reply #22018-01-09
Among the following options, the correct statements regarding the general construction layout plan are ( ACE ).   A. Large quantities of materials, finished products, semi-finished products, and machinery and equipment shall not be stored in such a way as to occupy the roads within the site or other safety facilities.
B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery shall be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily
Reply #32018-01-09
Among the following options, the correct statements regarding the general construction layout plan are ( ACE ).   A. Large quantities of materials, finished products, semi-finished products, and machinery and equipment shall not be stored in such a way as to occupy the roads within the site or other safety facilities.
B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery shall be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.