[Engineering Version] Daily Question 20180109
Thread Content
Among the following options, which statements regarding the general construction layout plan are correct? ( ) A. Large quantities of materials, finished products, semi-finished products, and machinery and equipment shall not be stored in such a way as to occupy the roads within the site or other safety facilities.B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery should be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily.
Correct answers: ACE
B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery shall be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily
B. With the consent of the project owner, it is permissible to use the roads and safety facilities within the site temporarily for storing large quantities of materials, finished products, semi-finished products, and machinery and equipment.
C. If a subcontractor truly needs to make changes to the overall construction layout, it must first submit an application to the main contractor; such changes can only be carried out with the main contractor’s approval.
D. For subcontractors assigned directly by the project owner, if they need to make changes to the overall construction layout, they must first submit an application to the project owner; such changes can only be carried out with the project owner’s approval.
E. Construction machinery shall be placed in the locations and along the routes specified in the overall construction layout, and it is not allowed to occupy the roads within the site arbitrarily