2018-01-21View Original

Thread Content

A certain project consists of three construction processes, namely a, b, and c, and is divided into four construction sections. The flow rhythms for these sections are 3 days, 3 days, and 6 days respectively; asynchronous flow construction is employed. The duration of this project is (  ) days.   A、21   B、48   C、30   D、20 Correct answer: A

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.