The installation of curtain walls should be inspected for the following items: ( ). a. Installation of the main structure and columns, as well as the joints between columns and beams, along with anti-corrosion treatment b. Installation of fire protection and insulation measures for the curtain wall c. Expansion joints, settlement joints, and seismic joints in the curtain wall d. Installation of lightning protection components for the curtain wall e. Waterproofing treatment for the curtain wall Answer: abcdb. Installation of fire protection and insulation measures for the curtain wall.
c. Creation of expansion joints, settlement joints, and seismic joints in the curtain wall.
d. Installation of lightning protection components for the curtain wall.
e. Waterproofing treatment of the curtain wall