[Engineering Version] Daily Question 20180502

2018-05-02View Original

Thread Content

A certain sub-project involves two construction processes, each of which is divided into 4 construction sections for flow construction. The flow rhythms are 3, 4, 3, 3 and 2, 5, 4, 3 days respectively; therefore, the flow step distance and the duration of the flow construction are ( ) days respectively.   A、3 and 16   B、3 and 17   C、5 and 18   D、5 and 19 Answer: D

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.