What are the requirements for applying for a construction permit? a) The approval procedures for the construction land have been completed ; b) Construction projects within the urban planning area that have obtained a planning permit ; c) In cases where demolition is required, the progress of such demolition meets the construction requirements ; d) The construction contractor has been identified ; e) There are construction drawings and technical documents sufficient to meet the construction requirements ; f) Specific measures to ensure project quality and safety ; g) The construction funds have been secured ; h) Other conditions stipulated by laws and administrative regulations.
Reply #22018-07-06
To apply for a construction permit, the following conditions must be met: 1. The approval procedures for the land used for the construction project have been completed. 2. Construction projects within the urban planning area have obtained a planning permit. 3. For those that require demolition, the progress of the demolition meets the construction requirements. 4. The construction company has been selected. 5. There are construction drawings and technical documents that meet the requirements of the construction. 6. Specific measures to ensure project quality and safety. 7. The funding for construction has been secured. 8. Other conditions stipulated by laws and administrative regulations.
Reply #32018-07-06
l. The approval procedures for the land use for this construction project have been completed. 2. Construction projects within the urban planning area have obtained a planning permit. 3. For those that require demolition, the progress of the demolition meets the construction requirements. 4. The construction company has been selected. 5. There are construction drawings and technical documents that meet the requirements of the construction. 6. Specific measures to ensure project quality and safety. 7. The funding for construction has been secured. 8. Other conditions stipulated by laws and administrative regulations.
Reply #42018-07-06
l. The approval procedures for the land use for this construction project have been completed. 2. Construction projects within the urban planning area have obtained a planning permit. 3. For those that require demolition, the progress of the demolition meets the construction requirements. 4. The construction company has been selected. 5. There are construction drawings and technical documents that meet the requirements of the construction. 6. Specific measures to ensure project quality and safety. 7. The funding for construction has been secured. 8. Other conditions stipulated by laws and administrative regulations.
Reply #52018-07-06
To apply for a construction permit, the following conditions must be met: 1. The approval procedures for the land used for the construction project have been completed. 2. Construction projects within the urban planning area have obtained a planning permit. 3. For those that require demolition, the progress of the demolition meets the construction requirements. 4. The construction company has been selected. 5. There are construction drawings and technical documents that meet the requirements of the construction. 6. Specific measures to ensure project quality and safety. 7. The funding for construction has been secured. 8. Other conditions stipulated by laws and administrative regulations. A construction permit is a document issued by the construction administration authority to authorize the commencement of construction work; it has legal validity. For any construction project that requires a construction permit in accordance with the Building Law of the People’s Republic of China, construction cannot begin without such a permit.
Reply #62018-07-06
(1) The approval procedures for the land use for this construction project have been completed; (2) The construction project planning permit has been obtained; (3) The construction site is generally ready for work, and any demolition that is required is being carried out at a pace that meets the construction requirements; (4) The construction company has been selected; (5) The construction drawings and technical documents necessary for the project are available, and the design documents have been reviewed in accordance with regulations; (6) There are specific measures in place to ensure project quality and safety, and the procedures for quality and safety supervision have been followed as required; (7) For projects that require supervision according to regulations, supervision services have been engaged; (8) The funding needed for the construction has been secured.
Reply #72018-07-06
1. Fixed asset investment permit issued by the planning department; 2. For construction projects within the urban planning area, the project site selection approval letter, the land use planning permit, and the construction project planning permit have already been obtained ; 3. There are construction drawings and technical documents that meet the requirements of the construction, and the design documents have been approved through the required review process. 4. The procedures for land acquisition and demolition have been completed ; 5. The bidding process has been completed, and the construction contractor has been selected ; 6. The project owner has appointed a construction supervisor, or the qualifications of the construction management agency appointed by the project owner have been approved; the project manager for this project has been determined ; 7. Funds, materials, and municipal utilities required for construction have been secured ; 8. The statistical registration procedures have been completed with the statistical authorities as required ; 9. Other required conditions have been met.
Reply #82018-07-06
1. If demolition is required, the progress of such demolition meets the construction requirements. 2. The funding for construction has been secured. 3. There are construction drawings and technical documents sufficient to meet the construction needs
Reply #92018-07-06
a) The approval procedures for the land use for construction have been completed; b) Construction projects within the urban planning area that have obtained a planning permit ; c) In cases where demolition is required, the progress of such demolition meets the construction requirements ; d) The construction contractor has been identified ; e) There are construction drawings and technical documents sufficient to meet the construction requirements.
Reply #102018-07-06
a) The approval procedures for the land use for construction have been completed; b) Construction projects within the urban planning area that have obtained a planning permit ; c) In cases where demolition is required, the progress of such demolition meets the construction requirements ; d) The construction contractor has been identified ; e) There are construction drawings and technical documents sufficient to meet the construction requirements.
Reply #112018-07-06
l. The approval procedures for the land use for this construction project have been completed. 2. Construction projects within the urban planning area have obtained a planning permit. 3. For those that require demolition, the progress of the demolition meets the construction requirements. 4. The construction company has been selected. 5. There are construction drawings and technical documents that meet the requirements of the construction. 6. Specific measures to ensure project quality and safety. 7. The funding for construction has been secured. 8. Other conditions stipulated by laws and administrative regulations.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.