Question post: Methods to quickly achieve compliance with the system dew point requirement

2020-05-01View Original

Thread Content

Dear experts, when preparing for production or starting up the system after maintenance, are there any methods that can ensure the system meets the dew point requirements in a short time, thereby saving nitrogen and reducing the time required for startup preparations?
Reply #22020-05-01
Let’s guess – your question is probably related to air separation units. If so, it is recommended to proceed to the next step in advance if it can be theoretically proven or guaranteed that the dew point after the molecular sieve will be at the required level. For reference.
Reply #32021-03-01
If using argon, the temperature of nitrogen should be kept below the maximum temperature specified in the equipment design.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.