Vertical pump maintenance?

2018-01-05View Original

Thread Content

As shown in the diagram, must the distance between the lifting beam and the motor be at least 3000 mm? Has anyone here ever worked on maintaining pumps?
Reply #22018-01-05
First, lower the motor; the remaining length will be around 3 meters.
Reply #32018-01-05
There are also requirements regarding the angle between the lifting ropes; it should not exceed 120° at most
Reply #42018-01-05
Hello, I’m referring to the 3000mm marked in red in the diagram.
Reply #52018-01-05
The hook is raised to a height of approximately 3000 mm above the motor fan cover
Reply #62018-01-07
At least 3m, and you also need to leave room for the length of the steel wire rope.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.