【In-depth Discussion on HaiChuan Modular Installation】Does the overall installation of a 18-meter-high flare count as modular construction?

2018-09-24View Original

Thread Content

In chemical plants, large flares are often lifted into place after the entire ground structure has been assembled, or they are assembled in sections and then put together in the air. Does the overall installation of large flares constitute modular construction?
Reply #22018-09-24
Welcome to participate in the series of discussions on the [Haichuan Modular Installation Discussion] thread – everyone is invited to join the conversations! https://bbs.hcbbs.com/thread-1773168-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #32018-09-24
This post was last edited by The wise are enlightened on 2018-9-24 at 20:18. It can be considered a relatively simple modular installation, with the structure, manufacturing processes, and equipment all integrated into modules; it’s likely that the electrical and control systems will need to be added later.
Reply #42018-09-24
This post was last edited by Zhizhi Ming on 2018-9-24 at 20:30. Due to the widespread use of large cranes (over 550 tons), the mainstream method for installing torches nowadays is sectional lifting. Due to the high costs associated with it (double-crane lifting + tail sliding, as well as the increased weight of the flare structure), overall lifting is being used less and less by installation companies.
Reply #52018-09-24
Question: What are the differences in the structural connections of the torch between the 4th and 5th floors?
Reply #62018-09-25
All the work, including electrical and instrumentation tasks as well as insulation work, is carried out on the ground; this is essentially similar to the process of installing components on the tower, and it cannot be considered modular construction.
Reply #72018-09-25
The insulated floor is ready. The cable needs to be threaded layer by layer in the last step. The PLC is a floor-mounted skid.
Reply #82018-09-25
The ignition system and the fuel gas pressure regulation skid are quite simple skids. Large torches indeed cannot have their electrical and instrumentation components installed all at once; small torches, on the other hand, can be completed right away, with sufficient length of cable left for installation on site. Our jacks all have cable slack.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.