Hengli Refining & Chemical ensures completion of the entire coal oil integration process by March 20. Four days ago, on February 7, the high-pressure pipeline testing for the wax oil hydrogenation unit in Hengli (Dalian) Petrochemical’s 20 million tons per year refining & chemical integration project, which is being constructed by Sinopec Refining & Chemical Engineering Group’s Tenth Construction Company, was successfully completed, marking the entry of the pipeline testing phase of this project into its final stage. The high-pressure pipeline that passed the pressure testing successfully this time starts from the 3 main frameworks of the wax oil hydrogenation unit, passes through heating furnaces, 48 air coolers, and 18 high-pressure devices, and connects 3 reactors. In total, there are 7 sections subject to pressure testing, with a length of 13 kilometers. The total length of pipe welding involved is 80,000 inches, the maximum diameter of the pipes is 1,050 millimeters, the highest pressure applied during testing is 35 MPa, and the amount of water used for testing was as much as 2,600 tons. This is the largest high-pressure pipeline system that Shijian Company has ever constructed in its history. Starting from New Year’s Eve, the project team worked tirelessly for 48 hours straight, and the high-pressure pipelines of the paraffin oil hydrogenation unit passed the pressure testing on the first attempt, earning high praise from both the owner and the supervisor. As of February 10, the project team had already completed in advance all the construction milestones required by the client during the Spring Festival period. At present, the project team will, in line with the overall commissioning objectives for each area of Hengli (Dalian) Petrochemical, make every effort to complete the remaining pressure testing tasks on the process pipelines, ensuring that both wax oil hydrogenation units can be successfully commissioned on schedule. The Spring Festival period is a critical time for the full commissioning of Hengli’s 20 million tons per year integrated refining and chemical processing project; Chairman Chen Jianhua visited various plant areas to discuss plans for accelerating operations with the site managers and foreign engineers. All personnel from the main units of Hengli Refining & Chemical, along with more than 10,000 highly skilled workers dispatched by over 100 project construction units, are working at the front lines, going all out to ensure quality and efficiency while racing against time to make progress. At present, refining units such as atmospheric and vacuum distillation and light hydrocarbon recovery, as well as related facilities like coal-to-hydrogen production, are successfully producing products, with 8 of these products already being sold on the market. The distillation systems of various downstream units have been fully connected for oil circulation, and all distillation furnaces have been ignited and heated up ; The circulation pumps of the reaction systems in various hydrogenation units for downstream products such as naphtha, aviation fuel, lubricating oil, diesel, wax oil, and residue have all been started successfully on one attempt and are operating stably, while the reaction heating furnaces have all been ignited for drying. The various units are gradually and fully entering operation. It is expected that by the end of February or before March 20, the entire production process will be fully operational, enabling full-capacity production and operation of the entire refining facility.
Reply #22019-02-18
On February 11, the first commissioning of compressor unit C4101 in the wax oil hydrogenation unit of Hengli (Dalian) Petrochemical’s 20 million tons per year integrated refining and petrochemical project, which was constructed by the 10th Construction Company of Refining and Chemical Engineering, was successful, marking the full commencement of compressor testing for this unit. It is understood that the compression units of this facility are centrifugal types for circulating hydrogen, with a total of 8 units, and they constitute the core of the entire facility. The maximum temperature of the medium gas in the compressor unit is 150 ℃, while the standard steam temperature is 450 ℃. As Hengli (Dalian) Petrochemical is located in the Changxing Island area of Dalian, the site has been subjected to low temperatures and severe cold since the Spring Festival, which has had a negative impact on the temperature of the steam used in the commissioning of the compression units, resulting in a slower progress in the commissioning process. To this end, the responsible persons for various aspects of the compressor unit in the project team worked closely with the owner and supervisor during the Spring Festival, continuously optimizing the commissioning plan. After multiple cycles of increasing steam temperature and pressure, the commissioning process gradually got on track. Ultimately, it was achieved that the compressor unit operated stably with all parameters within normal ranges, and the commissioning was successful on the first attempt. It became the first unit in the entire plant to undergo compressor unit commissioning, successfully meeting the owner’s set goals and earning unanimous recognition from all parties. During the installation of the compressor unit, the project team mobilized its most skilled personnel to carry out the work. All personnel involved in the construction maintained a commitment to excellence in their work. They created display boards showing the installation procedures for compressor units, the relevant regulations, and the performance specifications of these compressors, and hung them in prominent locations within the factory floor, serving as a constant reminder to the installers to pay close attention to every step of the process. At the same time, in accordance with the owner’s schedule requirements, the project team carefully detailed the daily work plans for each task team, ensuring that responsibilities were assigned to specific individuals. This approach helped keep the safety, quality, and progress of the compressor unit construction under control, thereby creating favorable conditions for the successful first commissioning of the compressor unit.
Reply #32019-02-18
Focus on progress while ensuring quality.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.