HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Do you know the amount of engineering work involved in Shen’s 500,000 tons/year coal-based ethanol project?

2022-06-15View Original

Thread Content

The Yanchang Petroleum Yushen 500,000 tons/year coal-based ethanol project adopts the dimethyl ether carbonylation ethanol technology jointly developed by Yanchang Petroleum and the Dalian Institute of Chemical Physics, Chinese Academy of Sciences, with an annual output of 500,000 tons of ethanol. The project has an investment of 6.98 billion yuan and is located in the southern area of ​​Qingshui Industrial Park, Yushen Industrial Park, Yulin City, Shaanxi Province, covering an area of ​​1,365 acres. The project officially started construction on November 6, 2018, and is scheduled to reach production and standards in 2022. The construction content includes the methanol joint center (coal unloading and storage, coal gasification device, conversion device, purification device, gas separation device, methanol device, sulfur device and other devices), ethanol device (dimethyl ether, carbonylation, hydrogenation, separation, compression, heating furnace, refrigeration station and other units), as well as the new parts of public works and auxiliary facilities, and is designed to convert 1.22 million tons of coal per year.
Reply #22022-06-15
The construction content includes the methanol joint center (coal unloading and storage, coal gasification device, conversion device, purification device, gas separation device, methanol device, sulfur device and other devices), ethanol device (dimethyl ether, carbonylation, hydrogenation, separation, compression, heating furnace, refrigeration station and other units), as well as the new parts of public works and auxiliary facilities, and is designed to convert 1.22 million tons of coal per year. Through the careful organization of the project department and the hard work of all participating units over the past two years, the "Civil Construction Battle" and "Installation Battle" and other goals and tasks have been completed. As of May 30, 2022, 29,636t of steel structure installation, 1,833 pieces of equipment, 433,397 meters of process pipelines, 1,416,736 inches of welding, 1,829 pressure test packages, 90% of electrical installation, and 80% of instrument installation have been completed, completing the task targets issued by the owner on schedule.
Reply #32022-06-23
There are 433,397 meters of process pipelines, 1,416,736 inches of welding volume, and 1,829 pressure test packages.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.