【Haichuan Heavy-Lift Installation Case】001—500-ton Module on Top of Huizhou Petrochemical Gasification Frame

2022-09-06View Original

Thread Content

Recently, the module lifting at the construction site of the Huizhou petrochemical project got off to a strong start. The first module at the lifting site – Module 1 – was slowly raised; once it reached a height of over 35 meters above the top of the gasification frame, the module had completed a 90-degree rotation and was now hovering there. Thereafter, alignment, temporary reinforcement, and welding were carried out, and the module lifting was completed successfully.
Reply #22022-09-06
Module 1 utilizes a deep prefabrication process; it is the heaviest, largest in volume, and deepest in prefabrication level module that the project team has ever constructed to date through on-site assembly followed by lifting. It consists of a two-story steel structure with 16 columns, having a total height of 12.0 m, a length of 33.0 m, and a width of 25.5 m, with a weight of 514.5 tons. On its two floors there are installed certain pipes and small equipment that have been completed. It is lifted to the 35.0-m-high frame for installation by a 1600-ton crawler crane standing tall on the north side of the vaporization frame. Module 1 has a total of 12 lifting points, which are arranged symmetrically in two areas at the top of the module; these points are connected via 12 sets of steel cables to the balance beam.
Reply #32022-09-27
Could someone share the advantages of modular installation? ! !
Reply #42022-10-11
The advantage is that the modules can be assembled on the ground, reducing the risks associated with working at heights and speeding up the process; the disadvantage is that it increases the risks related to large-scale lifting operations.
Reply #52022-10-11
Thanks for clearing up the doubt! :For the handshake, non-module installation tasks that involve working at heights should also take place at the “heights” within the platform’s interior area, right?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.