8 months to install 237 steel structural modules for the system utility tunnel at Nangang Ethylene Plant

2023-03-15View Original

Thread Content

On March 9, with the successful installation of the last module, K1C10, of the 1C pipe gallery – weighing 118 tons and measuring 27 meters in length – for the Tianjin Petrochemical Nangang Ethylene Project, the installation work on the steel structure modules manufactured in a \"prefabricated, modular\" manner for the 8 system pipe galleries of this project came to an end. Over an period of 8 months, a total of 237 such steel structure modules were installed, with a combined weight of over 20,000 tons.
Reply #22023-03-15
The extrusion granulation operation system has been upgraded to a full Chinese version, allowing for complete control over the operation process. It is necessary to understand communication and respond actively to @qq.com

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.