Fastest record for getting a vehicle running on a device of this type: 23 days! Full-scale commissioning of Xinye Nenghua’s 40,000 tons/year polyoxymethylene project

2023-07-17View Original

Thread Content

On July 9, Xinye Nenghua Company successfully completed the full-scale trial operation of the first phase of its polyoxymethylene production facility, with an investment of 1.3 billion yuan; this facility has a capacity of 40,000 tons per year, and the first batch of high-quality polyoxymethylene products was produced. This innovation not only filled the gap in Xinjiang’s polyoxymethylene market but also set a record for the fastest commissioning time of a similar facility in China, achieving this in just 23 days. On July 12, 50 tons of polyoxymethylene products were packaged and taken off the production line at Xinjiang Xinye Energy Chemical Co., Ltd.’s 40,000-ton/year polyoxymethylene production line – Xinjiang’s first such production line. These products became the first polyoxymethylene products manufactured by local enterprises in Xinjiang. The entire production process was completed in just 23 days, setting a new record for the fastest commissioning time of similar facilities in China, which was previously 30 days. The first phase of this project, involving a polyoxymethylene production line with an annual capacity of 40,000 tons, began construction in April 2021, with a total investment of 1.3 billion yuan ; The second-phase 60,000-ton/year polyoxymethylene project, with a total investment of 1.5 billion yuan, has now passed the energy-saving evaluation. It is a key project of the Xinjiang State-owned Assets Supervision and Administration Commission and the Xinjiang Production and Construction Corps, as well as a milestone project for Wujiaqu City in the Sixth Division of the Xinjiang Corps in its transformation from traditional coal chemical industry to a strategic new materials chemical industry. It is reported that the project utilizes the company’s abundant methanol resources and the low-pressure steam generated as a by-product of its operations to extend the industrial chain and produce coal-based new materials with higher added value – polyoxymethylene polymer resins. Coal, which costs several hundred yuan per ton, undergoes processing through a polyoxymethylene production line and thus undergoes a \"remarkable transformation,\" with its value rising to over 10,000 yuan per ton.
Reply #22023-07-17
The polyoxymethylene project, a strategic initiative key to the development of the new energy and chemical industry, involves a total investment of 2.8 billion yuan; it will be built in two phases to produce 100,000 tons per year of polyoxymethylene. In April 2021, the first phase of the project, with an investment of 1.3 billion yuan, namely a 40,000-ton/year polyoxymethylene production facility, began construction. The first-phase polyoxymethylene project includes 22 main sub-projects, covering process streams such as the formaldehyde unit, dilute aldehyde recovery, and the pentaerythritol unit. The project installed 668 sets of process equipment, with a total investment of 1.3 billion yuan, and the construction period was 2 years. At present, the second-phase project has passed the review by the energy-saving evaluation committee, and the procurement phase for the process package is underway. Once the entire polyoxymethylene project is completed, it will become the largest polyoxymethylene production base in the northwest region.
Reply #32023-07-17
The polyoxymethylene project, a strategic initiative key to the development of the new energy and chemical industry, involves a total investment of 2.8 billion yuan; it will be built in two phases to produce 100,000 tons per year of polyoxymethylene. In April 2021, the first phase of the project, with an investment of 1.3 billion yuan, namely a 40,000-ton/year polyoxymethylene production facility, began construction. The first-phase polyoxymethylene project includes 22 main sub-projects, covering process streams such as the formaldehyde unit, dilute aldehyde recovery, and the pentaerythritol unit. The project installed 668 sets of process equipment, with a total investment of 1.3 billion yuan, and the construction period was 2 years. At present, the second-phase project has passed the review by the energy-saving evaluation committee, and the procurement phase for the process package is underway. Once the entire polyoxymethylene project is completed, it will become the largest polyoxymethylene production base in the northwest region.
Reply #42023-07-17
Fill the gap in Huashì! Xinjiang’s first batch of polyoxymethylene products launched 2023-07-17 10:33·Nantong Runfeng Petrochemical On July 9, Xinye Nenghua Company successfully completed the full-scale trial operation of the first phase of its polyoxymethylene production facility, with an investment of 1.3 billion yuan; this facility has an annual production capacity of 40,000 tons, and the first batch of high-quality polyoxymethylene products was produced as a result. This innovation not only filled the gap in Xinjiang’s polyoxymethylene market but also set a record for the fastest commissioning time of a similar facility in China, achieving this in just 23 days. The polyoxymethylene project, a strategic initiative key to the development of the new energy and chemical industry, involves a total investment of 2.8 billion yuan; it will be built in two phases to produce 100,000 tons per year of polyoxymethylene. In April 2021, the first phase of the project, with an investment of 1.3 billion yuan, namely a 40,000-ton/year polyoxymethylene production facility, began construction. The first-phase polyoxymethylene project includes 22 main sub-projects, covering process streams such as the formaldehyde unit, dilute aldehyde recovery, and the pentaerythritol unit. The project installed 668 sets of process equipment, with a total investment of 1.3 billion yuan, and the construction period was 2 years. At present, the second-phase project has passed the review by the energy-saving evaluation committee, and the procurement phase for the process package is underway. Once the entire polyoxymethylene project is completed, it will become the largest polyoxymethylene production base in the northwest region. On June 8, the first phase of the polyoxymethylene project entered the feed-in commissioning stage. On June 17, the polyoxymethylene plant was fed with raw materials. On July 3, qualified products of triomethylenetetraoxane and dioxolane with purity levels of 99.9% and 99.99% were produced. On July 6, the polymerization system was successfully fed with materials, resulting in the production of crude polyoxymethylene. On July 9, pelletization was successful using the pelletizer, the entire polyoxymethylene production process was established, and the trial run with feed material was successful on the first attempt.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.