The first phase (Phase 2) of the chemical sector of the Songyuan Tianying integrated project for hydrogen, ammonia, and alcohol production via wind and solar energy has been approved for registration

2025-10-14View Original

Thread Content

The first phase (second stage) of the chemical sector of Tianying’s hydrogen, ammonia, and alcohol production project has been approved. On October 11, information on the Jilin Province Online Approval and Supervision Platform for Investment Projects indicated that the first phase (second stage) of Songyuan Tianying’s integrated wind, solar, energy storage, hydrogen, ammonia, and alcohol production project has been approved for registration. The total investment for this project is 3.7 billion yuan. The planned start date is August 2025, and the planned completion date is March 2028. The main construction scope and details include: the project will feature a methanol production facility with an annual capacity of 500,000 tons, as well as a hydrogen production facility with a capacity of 96,000 Nm³/h, along with various auxiliary production facilities. Public information shows that the first phase of the chemical section of Songyuan Tianying’s integrated wind, solar, hydrogen, ammonia, and methanol production project was registered in June 2024; it is planned to build a methanol production facility with an annual capacity of 170,000 tons, as well as a hydrogen production plant with a capacity of 56,000 Nm³/h.
Reply #22025-10-14
【Ten Years of Rapid Development in Chemical Equipment】2730-2025: The world’s first set! New breakthrough achieved in the pilot plant for producing acid and cement from third-generation phosphogypsum https://bbs.hcbbs.com/thread-5702721-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #32025-10-14
【Ten Years of Rapid Development in Chemical Equipment】The first intelligent inspection robot for storage tank bottoms in the petrochemical industry, 2731-2025, has been successfully deployed in actual operations. https://bbs.hcbbs.com/thread-5702794-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #42025-10-15
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2733 to 2025: Taigang Group achieves stable mass production of N10276, its \"king of nickel-based corrosion-resistant alloys\" https://bbs.hcbbs.com/thread-5702842-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #52025-10-15
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2733 to 2025: Taigang Group achieves stable mass production of N10276, its \"king of nickel-based corrosion-resistant alloys\" https://bbs.hcbbs.com/thread-5702842-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #62025-10-16
【Ten Years of Rapid Development in Chemical Processing Equipment】Dry separation systems for sulfate alkylation, 2735–2025: Complete sets of technologies https://bbs.hcbbs.com/thread-5702881-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #72025-10-16
【Ten Years of Rapid Development in Chemical Engineering Equipment】Acceptance of 2736-2025 long-shaft centrifugal pumps for oil fields completed; new advances achieved in water injection equipment for offshore platforms https://bbs.hcbbs.com/thread-5702942-1-1.html (Source: Haichuan Chemical Engineering Forum)
Reply #82025-10-17
【Ten Years of Rapid Development in Chemical Processing Equipment】The first VOCs (volatile organic compounds) flare gas recovery system for China’s coal chemical industry was successfully put into operation at Xinjiang Xinye Energy Chemical in the period 2027–2025. https://bbs.hcbbs.com/thread-5702973-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #92025-10-17
【Ten Years of Rapid Development in Chemical Engineering Equipment】2738-2025: \"Shenmu Machinery Develops China’s First Eight-Stage Multi-Axis Carbon Dioxide Compressor\", Contributing to the Successful Operation of the World’s Largest Coal-Fired Power Plant Carbon Capture Project https://bbs.hcbbs.com/thread-5702987-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #102025-10-17
【Ten Years of Rapid Development in Chemical Engineering Equipment】2738-2025: \"Shenmu Machinery Develops China’s First Eight-Stage Multi-Axis Carbon Dioxide Compressor\", Contributing to the Successful Operation of the World’s Largest Coal-Fired Power Plant Carbon Capture Project https://bbs.hcbbs.com/thread-5702987-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #112025-10-18
【Ten Years of Rapid Development in Chemical Engineering Equipment】2739-2025: Accelerating breakthroughs in challenging problems and technical bottlenecks; the Chinese Academy of Sciences launches an international scientific initiative on the biological conversion of carbon dioxide https://bbs.hcbbs.com/thread-5703002-1-1.html (Source: Haichuan Chemical Engineering Forum)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.