Purging of high-pressure coal slurry pipeline

2015-06-08View Original

Thread Content

This post was last edited by Leiyuhuo on 2015-6-8 at 12:54. For high-pressure nitrogen purging in high-pressure coal slurry pipelines, should the shut-off valve be placed before the isolation valve or after it?
Reply #22015-06-08
After closing the shut-off valve, since there is only one shut-off valve in the slurry pipeline and a slurry circulation has already been established during nitrogen purging, it is not possible to do so before the shut-off valve. If there are two cut-off valves, they should be placed between the two.
Reply #32015-06-08
This post was last edited by Leiyuhuo on 2015-6-8 at 12:54. It was my fault for not explaining my question clearly; I’ll edit it again.
Reply #42015-06-08
It could be added after the cut-off valve, or maybe it was drawn incorrectly?
Reply #52015-06-08
This post was last edited by *aodouzi on 2015-6-9 09:00*. *Inertia still plays a role here; it serves as an additional safeguard to prevent internal leakage in the valve.*
Reply #62015-06-09
Normally, this should be located in front of the valve

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.