Skid-mounted equipment units in the process flow diagram

2015-07-21View Original

Thread Content

Some equipment, such as vacuum units, are now available as complete systems. How should they be represented in the preliminary design when drawing process flow diagrams? Should it be drawn in detail, or some other representation?
Reply #22015-07-21
At the very least, the interface needs to be drawn, right? As for what’s inside the pry tool, will the manufacturer provide it, or will you specify it? In a complete flowchart, it is best to include everything, to facilitate understanding later on.
Reply #32015-07-21
Got it, thank you. It’s already installed; only the necessary procedures need to be completed. Drawings: lol
Reply #42015-07-21
Actually, I’ve seen both. If everything is drawn out in full, it’s easy to understand, but could there be anything that one doesn’t want others to know? For example, with patents and copyrights, are you worried that unauthorized people might cause the leakage of information? It’s not the case that everything has to be drawn in full; such situations do exist too! We welcome you to participate actively in the events – wealth and tangible rewards are waiting for you! Not only weird ideas can be shared – amazing ideas work too! It’s not just pictures that are allowed; drawings are also acceptable. The fun chemical engineering event “Spending Money”★★is now here in its second season★★ – a design sharing competition themed “Weird Ideas VS Amazing Ideas” under the category of “Chemical Engineering Processes”: http://bbs.hcbbs.com/thread-1419966-1-1.html
Reply #52015-07-21
During the preliminary design phase, squares are used as substitutes, but the corresponding connection ports must be drawn. Generally, after an inquiry, the manufacturer will send over the skid-mounted design drawings, which contain detailed flowcharts; the design can then be created based on those. When producing the construction drawings, there must not be just a single box – the client will think your skills are very poor

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.