What tasks need to be completed before the project is accepted for completion?
Reply #22015-07-22
I. On-site preparation work 1. Before the acceptance of each main construction phase, any construction holes in the walls must be properly filled in accordance with regulations, and records of the inspection of these concealed works must be kept. Decoration work shall not proceed until such inspections are completed. In cases where it is necessary to carry out the acceptance of the quality of each main construction phase in stages, the project manager of the construction unit must submit a written request to the quality supervision officers during the quality supervision briefing, and approval from the quality supervision agency is required. 2. The formwork for concrete structure projects should be removed and their surfaces cleaned thoroughly; any defects in the concrete structure should be rectified. 3. The floor elevation control lines should be clearly marked with ink lines and equipped with prominent markers. 4. All issues existing in the engineering technical documents have been fully rectified. 5. The construction work specified in the construction contract and design documents for the respective main and sub-projects has been completed, and the inspection and testing reports shall meet the requirements of current acceptance specifications and standards. 6. The embedding of various types of pipes in the installation work is complete; their positions and dimensions are accurate, and the corresponding testing has been carried out, with results that meet the specified requirements. 7. Before the acceptance of the main sub-projects, the interior plastering of the model room or model unit can be completed. II. Preparation of documents 1. The quality inspection report for the main structural components of the project should be prepared on the basis of the construction unit’s own inspections showing that everything is in order. After confirming that the self-inspections are satisfactory, the construction unit submits an application for project inspection to be approved by the supervisor; at the time of submitting this application, the relevant documents related to the quality inspection of the main structural components must also be submitted to the supervisor for review ; 2. After the acceptance application is approved by the supervisor, the acceptance date is determined, and the report materials for the sub-structure acceptance must be submitted to the supervisor one day in advance for review and to be stamped with the construction unit’s official seal ; 3. After the completion of the main structure work, the supervision unit shall conduct a quality assessment of the entire supervision process for the project and provide a quality evaluation report for the main structure. This report must be reviewed, signed, and stamped by the chief supervisor and the relevant responsible persons of the supervision unit. 4. The survey and design units shall inspect the survey and design documents as well as design changes. Verify whether the main structure of the project is in accordance with the design drawings and changes. 5. Complete archival materials for the main structural works, records of witness tests, and supervision documents ; Construction quality assurance documents ; Management data and evaluation data. 6. Inspection record of the concrete strength of the structural elements in the concrete structure sub-project. 7. Inspection record of the thickness of the reinforcement cover layer in the structural elements of the concrete structure sub-project. 8. The owner submits an application form for structural inspection to the local quality and safety supervision agency, requesting an intermediate inspection of the main structural works. 9. Under the supervision of the local quality and safety office, the chief supervision engineer or the project leader of the construction unit shall organize the project leaders and technical and quality supervisors from the survey and design units as well as the construction unit to carry out the acceptance together, in accordance with the design requirements and relevant construction acceptance standards.
Reply #32015-07-22
Thank you for the reply; it was very detailed. I’ve learned a lot
Reply #42015-07-22
Subject acceptance, subject acceptance, subject acceptance, subject acceptance – Preparation, preparation, preparation, preparation. 2.1 On-site preparation work: 2.1.1 Before the partial acceptance of the main structure, any construction holes in the walls must be properly filled in accordance with regulations, and records of the inspection of these concealed works must be kept. Decoration work shall not proceed until such inspections are completed. In cases where it is necessary to carry out partial quality inspections of the main structure in stages, the project manager of the construction unit must submit a written request to the quality supervision officers during the quality supervision briefing, and approval from the quality supervision agency is required. 2.1.2 The formwork for concrete structure projects should be removed and their surfaces cleaned thoroughly; any defects in the concrete structure should be rectified. 2.1.3 The floor elevation control lines shall be clearly marked with ink lines and equipped with prominent markers. 2.1.4 All issues existing in the engineering technical documents have been fully rectified. 2.1.5 The construction work specified in the construction contract and design documents for the respective main and sub-projects has been completed, and the inspection and testing reports shall meet the requirements of current acceptance specifications and standards. 2.1.6 All types of pipes in the installation work have been embedded, with accurate positions and dimensions; the corresponding testing has been completed, and its results meet the specified requirements. 2.1.7 Before the acceptance of the main sub-projects, the interior plastering of the sample room or sample unit can be completed. 2.2 Preparation of documents 2.2.1. The quality inspection report for the main structural components shall be prepared on the basis of the construction unit’s own inspections showing that the work is satisfactory. After confirming that the self-inspections are successful, the construction unit submits an application for project inspection to be approved by the supervisor; at the time of submitting the inspection request, the relevant documents related to the quality inspection of the main structural components must also be submitted to the supervisor for review ; 2.2.2. Once the acceptance application is approved by the supervisor, the acceptance date will be determined, and the report materials for the sub-structure acceptance shall be submitted to the supervisor one day in advance for review and stamped with the construction unit’s official seal ; 2.2.3 After the completion of the main structure works, the supervision unit shall conduct a quality assessment of the entire supervision process for the project and provide a quality evaluation report for the main structure; this report must be reviewed, signed, and sealed by the chief supervisor and the relevant responsible persons of the supervision unit. 2.2.4 The survey and design units shall inspect the survey and design documents as well as design changes. Verify whether the main structure of the project is in accordance with the design drawings and changes. 2.2.5 Complete engineering documentation for the main structure, documentation of witness tests, and supervision documents ; Construction quality assurance documents ; Management data and evaluation data. 2.2.6 Records of inspection for the strength of the concrete in the structural elements of the concrete structure sub-project. 2.2.7 Records of inspection for the thickness of the reinforcement cover layer in the structural elements of the concrete structure sub-project. 2.2.8 The owner submits an application form for structural inspection to the local quality and safety supervision agency, requesting an intermediate inspection of the main structural works. 2.2.8 Under the supervision of the local geological safety station, the chief supervision engineer or the project leader of the construction unit shall organize the project leaders and technical quality officers from the survey and design units as well as the construction unit to conduct the acceptance together, in accordance with the design requirements and relevant construction acceptance standards

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.