In the estimated total investment for the feasibility study, the project costs include construction costs, equipment acquisition costs, and installation costs. But should major materials such as instrumentation cables, process pipelines, valves, and flanges be classified under equipment acquisition costs or installation costs?
Reply #22015-08-28
Materials such as instrument cables, process pipelines, valves, flanges, etc. are classified under installation costs.
Reply #32015-09-11
Materials such as instrument cables, process pipelines, valves, flanges, etc. are classified under the costs associated with installation work. Generally, valves with a diameter of DN300 or larger are considered equipment by some design institutes; in that case, those valves are included in the costs related to equipment acquisition

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.