How to establish a liquid level in an propylene refrigeration compressor? After liquid propylene is introduced into the third-stage tank following stamping, how should the liquid level be established in the second-stage tank, and to what level needs it to be stamped? Does a section of the tank need to be stamped, and if so, to what extent? The set pressure of the safety valves in each section varies during this process – how should this issue be addressed?
Reply #22015-09-10
Before starting up the propylene unit, pressurize the entire system to 0.6 Mpa; fill the three-stage tanks to 60% capacity with liquid. As propylene liquid is introduced by the various users, additional liquid should be added to these three stages
Reply #32015-09-15
Fill the two-stage tanks according to the pressure difference; before starting up, apply 6 kilograms of pressure to the entire system. You can check the setting pressure of the safety valves in each tank – if it is higher than that setting value, it is possible to refrain from activating the safety valves for now
Reply #42015-11-02
The previous tank does not need to be filled with liquid; it is sufficient as long as the quench tank has a liquid level.
Reply #52015-11-02
Before starting the machine, three tanks can be filled to 80% capacity, and two tanks to 60% capacity. If the operator is inexperienced, it’s advisable not to stop the propylene pumps in the tank area, so that propylene can be added promptly

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.