Let’s work on Questions 02-20 from the 2015 First-Class Constructor Examination – Multiple Choice Questions on Laws and Regulations, questions 06-10

2015-10-13View Original

Thread Content

I have gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to increase everyone’s interest in participating. Instead of posting them all at once, I’ll present five multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate! ****************************************** 6. Regarding the activities that can be carried out within the protection zones and construction control areas of cultural heritage sites, which statement is correct? A. Blasting operations are not permitted within the protection area of cultural relics sites or in certain areas surrounding them. B. To carry out blasting operations within the protection area of nationally designated key cultural relics sites, approval from the State Council is required. C. If blasting operations are necessary within the protection area of a cultural relics site due to special circumstances, approval must be obtained from the people’s government responsible for overseeing that cultural relics site. D. To carry out blasting operations within the protection area of key cultural relics sites at the provincial, autonomous region, or municipal level, approval from the State Council’s cultural relics authorities is required. 【Construction Project Regulations – Answer】C 【Construction Project Regulations – Answer Explanation】This question deals with the regulations regarding construction activities within the protection areas and construction control zones of cultural relics sites. The Law on the Protection of Cultural Relics stipulates that no other construction projects, nor activities such as blasting, drilling, or excavation, shall be carried out within the protection areas of cultural relic protection units. However, in cases where it is necessary to carry out other construction projects, or activities such as blasting, drilling, and excavation within the protection area of a cultural heritage site due to special circumstances, it is essential to ensure the safety of that cultural heritage site. Such actions must be approved by the people’s government responsible for overseeing that cultural heritage site, and prior to approval, consent from the cultural relics administration department at the higher level must be obtained. When carrying out such activities within the protection area of a nationally important cultural heritage site, approval from the people’s government of the province, autonomous region, or municipality directly under the Central Government is required, with consent from the State Council’s cultural relics administration department needed prior to approval. See page P207 of the textbook. 7. A highway project was put up for bidding, and bids were accepted after the opening of bids. A. The bid evaluation committee requests that bidders provide written clarifications for any unclear points. B. Bidders offer additional favorable terms. C. Bidders withdraw their bid documents. D. The tenderer changes the methods specified in the tender documents for bid evaluation and selection. 【Construction Project Laws – Answer】A 【Construction Project Laws – Explanation of Answers】This question relates to the basic procedures for conducting tenders. The bid evaluation committee may request the bidder to provide necessary clarifications or explanations for any unclear contents in the bid document, provided that such clarifications or explanations do not go beyond the scope of the bid document nor alter its substantive content. Refer to page P87.8 of the textbook. According to the Water Pollution Prevention and Control Law, when an enterprise or institution experiences an accident or some other disaster-like event that results in, or may result in, water pollution, it must immediately activate its own emergency plan, take emergency measures, and report the situation to the local people’s government at the county level or above, or to the environmental protection authorities. A. Location of the entity B. Area affected by pollution C. Registration location of the entity D. Location where the accident occurred 【Construction Project Laws – Answer】D 【Construction Project Laws – Explanation of Answers】This question relates to the prevention and control of water pollution. The Water Pollution Prevention and Control Law stipulates that when an enterprise or institution experiences an accident or some other sudden incident that may lead to water pollution, it must immediately activate its own emergency plan, take emergency measures, and report the situation to the local people’s government at the county level or above where the incident occurred, or to the competent environmental protection authority. See page P189 of the textbook. 9. According to the Contract Law, when a creditor transfers the rights under a contract to a third party, A. It requires the consent of the creditor, and notarization is necessary. B. It does not require the debtor’s consent, nor is it necessary to notify the debtor. C. The debtor’s consent is not required, but notarization is necessary. D. It does not require the creditor’s consent, but the debtor must be notified. 【Construction Project Laws – Answer】D 【Construction Project Laws – Explanation of Answers】This question deals with the performance of contracts, their modification, and the transfer of rights and obligations. The Contract Law stipulates that when a creditor transfers its rights, it shall notify the debtor. Without notice, such transfer has no effect on the debtor. See textbook P133. 10. Among the objects protected by intellectual property law listed below, which one falls under patent protection? A. New technologies developed by construction companies B. Cost estimation software developed by construction companies C. Bid documents prepared by construction companies D. Supervision plans prepared by supervision companies 【Construction Project Laws – Answer Key】 A 【Construction Project Laws – Answer Explanation】 This question relates to patent rights. China’s Patent Law protects patent rights for inventions and creations, stipulating that such inventions and creations include inventions, utility models, and design patents. Options BCD fall under copyright. See pages P26, 30–31 of the textbook.
Reply #22015-10-13
Cultural heritage protection, environmental protection, contract law, intellectual property law
Reply #32015-10-13
Bro, are you talking about the key points of the exam again?
Reply #42015-10-13
6、C 7、A 8、D 9、D 10、A
Reply #52015-10-13
Bingo, another full match – you’re really good at this
Reply #62015-10-13
There are still many things that are vague to me :Q
Reply #72015-10-14
6、C 7、A 8、D 9、D 10、 A
Reply #82015-10-15
6、D 7、A. The bid evaluation committee requests bidders to provide written clarifications for any unclear points. 8、D. The location where the accident occurred. 9、D. No consent from the creditors is required, but the debtor must be notified. 10、A. New technologies developed by construction companies
Reply #92015-10-19
6、C 7、A 8、D 9、D 10、 A

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.