Purging of large-diameter long-distance pipelines

2015-10-15View Original

Thread Content

1. Long-distance pipeline (approximately 5 km), with a relatively large diameter, but less than 600; purged with air. Question: Due to the large elevation differences along the entire length of the pipeline, is it necessary to purge it in sections before ascending? 2. For the same long-distance pipeline, are dredging measures necessary in the design?
Reply #22015-10-15
Pressure needs to be applied in stages; otherwise, it won’t be sufficient. For long-distance pipelines, dredging is also taken into consideration, using pigging devices with scrapers.
Reply #32015-10-15
1. Purging should be carried out in segments, with special attention paid to the areas with elbows. 2. For such long-distance pipelines, measures for dredging must be taken into account during design; dredging holes should be provided to facilitate cleaning during maintenance.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.