【Daily Question】Question from Issue 20151104

2015-11-04View Original

Thread Content

Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. The time during which the mortar mixer runs idle due to workers failing to supply material in a timely manner is considered part of the machine’s operating time consumption ( ). A. Effective working time B. Downtime not caused by construction activities C. Extra working time D. Working time under low load 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-04
The time during which the mortar mixer runs idly due to workers failing to supply material in a timely manner is included in (D) of the machine’s operating time consumption. A. Effective working time B. Downtime not caused by construction itself C. Extra working time D. Working time under low load
Reply #32015-11-04
When the mortar mixer is in operation, the time during which it runs idly due to workers failing to supply material in a timely manner is considered part of the mechanical operating time consumption (C, excess operating time).
Reply #42015-11-04
The time during which the mortar mixer runs idly due to workers failing to supply material in a timely manner is considered part of the machine’s operating time consumption (C).
Reply #52015-11-04
When the mortar mixer is in operation, the time during which it runs idly due to workers failing to supply material in a timely manner is included in the mechanical operating time consumption (C). A. Effective working time B. Downtime not caused by construction itself C. Extra working time D. Working time under low load
Reply #62015-11-04
C. Extra working hours. -------------------------------------
Reply #72015-11-04
C, extra working hours!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
Reply #82015-11-04
The answer is C................................
Reply #92015-11-04
When the mortar mixer is in operation, the time during which it runs idly due to workers failing to supply material in a timely manner is considered part of the mechanical operating time consumption (C, excess operating time).
Reply #102015-11-04
My answer: B. . . . . . . . . . . . . . . . .
Reply #112015-11-04
The time during which the mortar mixer runs idle due to workers failing to supply material in a timely manner is considered part of the machine’s operating time consumption ( ). D. Working time at low load

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.