Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Regarding the statement on considering a contingency fund when preparing a cost plan for construction projects, which one is correct? A. Consider only a total reserve fund for the entire project, to allow for flexible use of funds. B. Based on an analysis of the risks associated with each individual task, consider a reserve fund only for some of those tasks. C. Both a total reserve fund for the project as a whole and appropriate contingency funds for individual tasks should be established. D. No reserve fund is considered for the entire project; instead, the construction company handles this matter on its own. [Production and Management Division] Seeking moderators and technical discussants to join us
Reply #22015-11-09
Regarding the statement on considering a contingency fund when preparing a cost plan for construction projects, the correct option is (C): it is necessary to establish an overall contingency fund for the project as a whole, while also allocating an appropriate amount of unforeseen expenses for individual tasks.
Reply #32015-11-09
Regarding the statement on considering a contingency fund when preparing a cost plan for construction projects, the correct answer is (C). A. Consider only a total contingency fund for the entire project, to allow for flexible use of funds. B. Based on an analysis of the risks associated with each individual task, consider a contingency fund only for some of those tasks. C. Both a total contingency fund for the project as a whole and appropriate unforeseen expenses for individual tasks should be taken into account. D. Do not consider a contingency fund for the entire project; instead, let the construction company handle it uniformly
Reply #42015-11-09
C-----------------------------------------------
Reply #52015-11-09
Regarding the statement on considering a contingency fund when preparing a cost plan for construction projects, the correct answer is (C)
Reply #62015-11-09
C. It is necessary to consider a total contingency fund for the entire project, as well as to allocate appropriate amounts for unforeseen expenses within each individual task
Reply #72015-11-09
Regarding the statement on considering a contingency fund when preparing a construction project cost plan, the correct answer is (c). A. Consider only a total contingency fund for the entire project, to allow for flexible use of funds. B. Based on an analysis of the risks associated with each individual task, consider a contingency fund only for some of those tasks. C. Both a total contingency fund for the project as a whole and appropriate unforeseen expenses for individual tasks should be taken into account. D. Do not consider a contingency fund for the entire project; instead, let the construction company handle it uniformly
Reply #82015-11-09
Regarding the statement on considering a contingency fund when preparing a cost plan for construction projects, the correct answer is (C).
Reply #92015-11-09
The correct answer is C :lol:lol:lol

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.