HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

【Daily Question】Question from Issue 20151117

2015-11-18View Original

Thread Content

Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of ( ) during construction and comply with its overall project management. A. Owner B. Designer C. General contractor D. Project supervisor 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of (A) during construction and comply with its overall project management. A. Owner B. Designer C. General contractor D. Project supervisor
Reply #32015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of ( ) during construction and comply with its overall project management. C, General construction contractor
Reply #42015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of (A) during construction and comply with its overall project management. A. Owner B. Designer C. General contractor D. Project supervisor
Reply #52015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of (A) during construction and comply with its overall project management. A. Owner B. Designer C. General contractor D. Project supervisor
Reply #62015-11-18
C. General construction contractor. -------------------------
Reply #72015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of (c) during construction and comply with its overall project management.
Reply #82015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must accept work instructions from (C, the general contractor) during construction and comply with its overall project management.
Reply #92015-11-18
C, the general contractor for construction. Correct answer: The general contractor is responsible for the overall execution and organization of the construction work assigned to them, while the subcontractors are responsible for carrying out the subcontracted tasks specified in the contract, as well as the corresponding project management tasks. If a general construction contract or a general construction management approach is adopted, the subcontractor (whether it is a regular subcontractor or one designated by the owner) must respect the work instructions of the general contractor or the general construction manager and comply with their overall project management.
Reply #102015-11-18
For a construction project carried out under the general contracting model, where the electrical equipment is purchased and installed by a subcontractor designated by the owner, the subcontractor must follow the work instructions of (C) during construction and comply with its overall project management. The general construction contractor assumes overall responsibility for the execution and organization of the construction work assigned to it, while the subcontractors are responsible for carrying out the subcontracted tasks specified in the contract, as well as the corresponding project management tasks. If a general construction contract or a general construction management model is adopted, the subcontractor (whether it is a regular subcontractor or one designated by the owner) must accept the work instructions from the general contractor or the general construction manager and comply with their overall project management.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.