Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least ( ) days in advance. A.5 B,7 C.14 D.28 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-30
According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least (a) days in advance. A.5 B,7 C.14 D.28
Reply #32015-11-30
According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least (A) days in advance. A.5 B,7 C.14 D.28
Reply #42015-11-30
According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least (B) days in advance. A.5 B,7 C.14 D.28
Reply #52015-11-30
According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least (B) days in advance.
Reply #62015-11-30
B, 7.----------------------------
Reply #72015-11-30
When the project manager authorizes his subordinates to carry out a certain task due to special circumstances, he shall give written notice to the supervisor at least (B, 7) days in advance.
Reply #82015-11-30
My answer: C. . . . . . . . . . . . .
Reply #92015-11-30
According to the \"Construction Project Contract (Model Text)\」(GF-2013-0201), when the project manager, due to special circumstances, authorizes his subordinates to carry out certain tasks, he shall give written notice to the supervisor at least (B) days in advance.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.