Thread Content
Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. According to the Standard Construction Bidding Documents, regarding the suspension of construction, which statement is correct? A. In the event of a suspension of work caused by the employer, the contractor has the right to request an extension of the deadline and/or an increase in costs, but shall not claim compensation for profits. B. If the suspension of work is caused by the employer, the contractor is not responsible for protecting the work during that period. C. In case of an emergency resulting from a suspension caused by the employer, the contractor may suspend work first and promptly submit a written request to the supervisor regarding this suspension. D. In the event that unforeseen circumstances arise that require a suspension of work, all responsibilities lie with the employer. [Production and Management Division] Seeking moderators and technical discussants to join us
According to the Standard Construction Bidding Documents, regarding the suspension of construction, the correct statement is (C). A. In the event of a suspension of work caused by the employer, the contractor has the right to request an extension of the deadline and/or an increase in costs, but shall not claim compensation for profits. B. If the suspension of work is caused by the employer, the contractor is not responsible for protecting the work during that period of suspension. C. In case of an emergency resulting from a suspension caused by the employer, the contractor may suspend work first and promptly submit a written request to the supervisor regarding such suspension. D. In the event that unexpected circumstances arise that require a suspension of work, all responsibilities lie with the employer
In the event of an emergency that results in a suspension of work due to reasons on the part of the employer, the contractor may suspend work first and submit a written request to the supervisor for such suspension without delay
According to the Standard Construction Bidding Documents, regarding the suspension of work, the correct statement is (C: In case of an emergency that leads to a suspension of work due to reasons on the part of the employer, the contractor may suspend work first and submit a written request to the supervisor for such suspension without delay).
C. In the event of an emergency that results in a suspension of work due to reasons on the part of the employer, the contractor may suspend work first and submit a written request to the supervisor for such suspension without delay.
My answer: C. . . . . . . . .
According to the Standard Construction Bidding Documents, regarding the suspension of construction, the correct statement is (C).
According to the Standard Construction Bidding Documents, regarding the suspension of construction, which statement is correct? In the event of an emergency that results in a suspension of work due to reasons on the part of the employer, the contractor may suspend work first and submit a written request to the supervisor for such suspension without delay
According to the Standard Construction Bidding Documents, regarding the suspension of construction, the correct statement is (C).
In the event of an emergency that results in a suspension of work due to reasons on the part of the employer, the contractor may suspend work first and submit a written request to the supervisor for such suspension without delay
According to the Standard Construction Bidding Documents, regarding the suspension of construction, the correct statement is (c). A. In the event of a suspension of work caused by the employer, the contractor has the right to request an extension of the deadline and/or an increase in costs, but shall not claim compensation for profits === Compensation for reasonable profits can be requested. B. When a suspension of work is caused by the employer, the contractor is not responsible for protecting the work during that period -- The contractor is responsible and must also apply for compensation for related costs. C. In case of an emergency resulting from a suspension caused by the employer, the contractor may suspend work first and promptly submit a written request to the supervisor regarding this suspension. D. In the event that unexpected circumstances arise that require a suspension of work, all responsibilities lie with the employer