Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the causes of such deviations, an analysis of the responsibilities for those deviations, and ( ). A. Comparison of contract deviations for different projects B. Analysis of the tracking status of deviations C. Analysis of trends in contract implementation D. Analysis of the owner’s attitude toward contract deviations 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22016-01-07
C. Contract implementation trend analysis~~~~~~~~~
Reply #32016-01-07
The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the reasons for such deviations, an analysis of the responsibilities for those deviations, and (C).
Reply #42016-01-07
The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the reasons for such deviations, an analysis of the responsibilities for those deviations, and (C). A. Comparison of contract deviations for different projects B. Analysis of the tracking status of deviations C. Analysis of contract implementation trends D. Analysis of the owner’s attitude toward contract deviations
Reply #52016-01-07
The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the causes of such deviations, an analysis of the responsibilities for those deviations, and (c). A. Comparison of contract deviations for different projects B. Analysis of the tracking status of deviations C. Analysis of contract implementation trends D. Analysis of the owner’s attitude toward contract deviations
Reply #62016-01-07
The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the reasons for such deviations, an analysis of the responsibilities for those deviations, and (C). A. Comparison of contract deviations for different projects B. Analysis of the tracking status of deviations C. Analysis of contract implementation trends D. Analysis of the owner’s attitude toward contract deviations
Reply #72016-01-07
C. Contract implementation trend analysis 
Reply #82016-01-07
The contents of the analysis on deviations in the implementation of a construction contract include an analysis of the reasons for such deviations, an analysis of the responsibilities for those deviations, and (C) an analysis of the trends in contract implementation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.