Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is (  ) days behind the planned schedule.   A.3 B.5 C.8 D.10
Reply #22016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is ( B ) days behind the planned schedule.   A.3 B.5 C.8 D.10
Reply #32016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is (  D.10  ) days behind the planned schedule.
Reply #42016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is ( D ) days behind the planned schedule.   A.3 B.5 C.8 D.10
Reply #52016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is ( D ) days behind the planned schedule.   A.3 B.5 C.8 D.10
Reply #62016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is ( D ) days behind the planned schedule.   A.3 B.5 C.8 D.10
Reply #72016-01-23
It is known that in the network plan of a certain construction project, task A has a free float of 5 days and a total float of 7 days. When checking the construction progress, the supervision engineer found that only this task was behind schedule, and this delay affected the total project duration by 3 days; therefore, the actual progress of this task is ( D ) days behind the planned schedule.   A.3 B.5 C.8 D.10

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.