【Daily Question】Chemical Engineering Principles 326: Boiler Blowdown (February 24)

2016-02-24View Original

Thread Content

This post was last edited by “Back to Cambridge” on February 27, 2016, at 11:26. Starting today, the Chemical Engineering Theory section is launching the “Question of the Day” activity, aimed at helping everyone reinforce their basic knowledge in chemical engineering. Subsequently, series such as “Fundamentals of Chemical Engineering”, “Mass Transfer and Separation”, “Chemical Thermodynamics”, and “Chemical Process Technology” will also be introduced. We hope for your active participation! Wishing you all a Merry Christmas~~ For replies to the “Question of the Day” activity, answers can be viewed directly; however, the thread will be closed after one day! ! To encourage continued participation from everyone this year! You get 3 wealth rewards just for participating, and an additional 4 wealth points for correct answers~~~ Short answer question: What are the various methods of slag removal in boilers? What are their respective functions? For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.
Reply #22016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.
Reply #32016-02-24
(1) Continuous discharge: Continuous discharge is also known as continuous effluent release. It is the continuous discharge of boiler water from the drum. The main purpose of this blowdown is to prevent the salt content (or silicon content) in the boiler water from becoming too high; it also helps to remove fine, suspended sludge from the boiler water. Continuous drainage is taken from the drum because, during operation, the boiler water in the drum has a high salt content (or silicon content). (2) Regular sewage discharge: Regular sewage discharge is also known as fixed-discharge. This method of blowdown involves periodically discharging a portion of the boiler water from the lowest point in the boiler water circulation system (e.g., from the lower header of the water wall). The main purpose of regular sewage discharge is to remove sludge from the water. Regular sewage discharge is carried out in short periods each time, generally controlled between 0.5 and 1 minute. Excessive discharge time or too large an opening can affect the safety of the boiler water circulation. Periodic blowdown can also be used as a measure to rapidly reduce the salt content in boiler water, thereby compensating for the limitations of continuous blowdown. During the initial operation of a newly installed boiler, or when starting up an old boiler, it is often necessary to increase the frequency of regular blowdown in order to remove impurities such as rust and other sediment from the boiler water.
Reply #42016-02-24
There are two methods of blowdown: continuous blowdown and intermittent blowdown. Their purposes are as follows: to prevent the salt content (or silicon content) in the boiler water from becoming too high; at the same time, it helps to remove fine suspended sludge from the boiler water; To eliminate water slag.
Reply #52016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.
Reply #62016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.
Reply #72016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.
Reply #82016-02-24
Boiler blowdown refers to the operation of discharging a portion of the boiler water and replacing it with an equal amount of feedwater, which is carried out regularly during boiler operation in order to keep the salt content (or silicon content) of the boiler water within acceptable limits and to remove impurities from the water. Boilers require blowdown because, during operation, the impurities carried by the feedwater into the boiler remain essentially in the boiler water. As operating time increases, if no measures are taken, the impurities in the boiler water will continue to accumulate. When the salt content (or silicon content) in it exceeds a certain value, it will degrade the quality of the steam. When there is an excessive amount of sludge in the boiler water, it not only affects the quality of the steam but may also cause blockages in the boiler tubes, threatening the safe operation of the boiler. Therefore, during operation, boilers must be properly blowdowned to reduce impurities such as salt content in the boiler water. Boiler blowdown can be carried out in two ways: continuous blowdown and periodic blowdown. (1) Continuous discharge: Continuous discharge is also known as continuous effluent release. It is the continuous discharge of boiler water from the drum. The main purpose of this blowdown is to prevent the salt content (or silicon content) in the boiler water from becoming too high; it also helps to remove fine, suspended sludge from the boiler water. Continuous drainage is taken from the drum because, during operation, the boiler water in the drum has a high salt content (or silicon content). (2) Regular sewage discharge: Regular sewage discharge is also known as fixed-discharge. This method of blowdown involves periodically discharging a portion of the boiler water from the lowest point in the boiler water circulation system (e.g., from the lower header of the water wall). The main purpose of regular sewage discharge is to remove sludge from the water. Regular sewage discharge is carried out in short periods each time, generally controlled between 0.5 and 1 minute. Excessive discharge time or too large an opening can affect the safety of the boiler water circulation. Periodic blowdown can also be used as a measure to rapidly reduce the salt content in boiler water, thereby compensating for the limitations of continuous blowdown. During the initial operation of a newly installed boiler, or when starting up an old boiler, it is often necessary to increase the frequency of regular blowdown in order to remove impurities such as rust and other sediment from the boiler water.
Reply #92016-02-24
Continuous discharge and periodic discharge. Continuous discharge involves continuously releasing boiler water with high salt and silicon content from the drum, in order to prevent contamination of the steam; it also allows for the removal of some of the suspended impurities present in the boiler water ; Regular sewage discharge involves periodically removing the sedimented impurities from the lower part of the boiler water from the lowest point of the boiler water circulation system.
Reply #102016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, with each blowdown session generally lasting no more than 0.5–1.0 minutes.
Reply #112016-02-24
For drum boilers, the blowdown methods include continuous blowdown and periodic blowdown. Continuous drainage involves the continuous discharge of boiler water from the drum. The purpose of this process is to prevent excessive levels of salts and silicon in the boiler water, as well as to remove any fine or suspended sediment. The purpose of periodic blowdown is to remove sludge, therefore the blowdown point is located at the bottom of the water circulation system, such as at the lower header of the water wall. Periodic blowdown should be carried out when the boiler is operating at low load, and each blowdown session generally lasts no more than 0.5–1.0 minutes.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.