Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Multiple-choice question: Regarding the roles of an implementation construction plan, which of the following statements are correct? ( ) A. As a basis for preparing the construction schedule for a specific project B. To establish the overall construction timeline goals C. To determine the resource requirements for a given month D. To define the specific arrangements for construction tasks E. To set the timeline goals for milestone events 【Haichuan Thanksgiving】--Production Division The Production and Management Division is seeking moderators and technical discussants to join us
Reply #22016-03-08
Regarding the statements on the role of an implementation construction plan, the correct ones are (CD). A. As a basis for preparing the construction progress plan for the specific project B. To establish the overall construction progress objectives C. To determine the resource requirements for a given month D. To define the specific arrangements for construction activities E. To set the progress targets for milestone events
Reply #32016-03-08
C. Determine the resource requirements for one month of operation. D. Determine the specific schedule for the construction work
Reply #42016-03-08
This post was last edited by zhaozq2015 on 2016-3-8 15:30. B C
Reply #52016-03-08
Regarding the roles of the implementation construction plan, the correct options are (C D). A. As a basis for preparing the construction progress plan for the specific project B. To establish the overall construction progress objectives C. To determine the resource requirements for a given month D. To define the specific arrangements for construction activities E. To set the progress targets for milestone events
Reply #62016-03-08
Regarding the roles of implementing a construction plan, the correct options are (cd). C. Determine the resource requirements for one month of operation. D. Determine the specific schedule for the construction work
Reply #72016-03-08
Regarding the roles of the implementation construction plan, the correct options are (C D). A. As a basis for preparing the construction progress plan for the specific project B. To establish the overall construction progress objectives C. To determine the resource requirements for a given month D. To define the specific arrangements for construction activities E. To set the progress targets for milestone events

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.