Special plan for the new workshop

2016-03-08View Original

Thread Content

Today there was an inspection of the new workshop, and the experts said that it lacked a specific emergency plan for this workshop! The company’s various plans have just been revised and filed; there has never been a plan that covers just one workshop! To create a special plan just for one workshop – what on earth is the point of that?
Reply #22016-03-08
Experts always bring up something during the inspection.....
Reply #32016-03-08
If the new workshop adopts new technologies as well as new processes and materials that are not covered in the company’s existing plans, it is necessary to develop a new, targeted plan for that workshop.
Reply #42016-03-08
New workshop? If the original plant-level plan does not contain relevant information, then revise the plant-level plan and add it. These things are all the same; it’s just about creating a framework.
Reply #52016-03-09
May I ask, is this a safety verification? Is what is produced hazardous? And is your workshop considered a critical facility, a key area? ; Can it constitute a major hazard source? Are the materials involved covered in previous plans?
Reply #62016-03-10
The company’s comprehensive emergency plan should include an emergency plan for the new factory; if not, a specialized plan tailored to its characteristics needs to be developed. What the experts suggested is reasonable and well-founded – it is indeed necessary
Reply #72016-03-10
Included in it – when it was revised, the workshop had already been built and all the raw materials required had been determined, so they were included in the document!
Reply #82016-03-10
It’s a new workshop; considerations were already taken into account and included during the revisions, and it was also documented. I don’t quite understand it either
Reply #92016-03-10
The product is not hazardous; it only uses hazardous materials. It also does not constitute a major hazard source. The workshop should be treated as a key area
Reply #102016-03-10
Comprehensive plans that include new workshops must take into account any modifications that are needed; they should be incorporated together to avoid hassle. I didn’t expect that separate work would still be required
Reply #112016-03-10
If the comprehensive plan already includes the new workshop, it should be included together; in that case, there should be no need to handle it separately.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.