HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

【Daily Topic】【Civil Engineering Version 20160526】

2016-05-26View Original

Thread Content

Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Correctness check: To ensure tight bonding between the upper and lower layers of concrete in layered pouring, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. (  )
Reply #22016-05-26
To ensure a tight bond between the upper and lower layers of concrete in layered pouring, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. Right
Reply #32016-05-26
To ensure a tight bond between the upper and lower layers of concrete poured in layers, the vibrator should be inserted into the lower layer (the freshly poured concrete) to a depth of at least 50 mm. (√)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.