Can the bypass of the metal tube rotameter be removed?

2016-07-22View Original

Thread Content

For the renovation of the factory project, due to limited space on site, it is considered to eliminate the bypass for the rotameter. Since I am not aware of the amount of maintenance required in the future, could the teachers please cancel it?
Reply #22016-07-22
It’s hard to say; it depends on whether a failure of the rotameter will have an impact on the existing process; If immediate handling is required, a bypass must be installed; if it has no impact on production, it can be omitted ; Personally, I think it should be possible to cancel this: generally, the requirements in places where rotameters are used are not that high ; (If it is not necessary to replace the component immediately due to the fault, or if shutting down this pipeline for a while has no impact on the process)
Reply #32016-07-22
The company’s projects involve the production of dyeing and printing intermediates; I have had limited experience with metal tube rotameters in the past. Consider removing the instrument bypass for the pure water pipeline. It’s just my personal consideration; I’m not sure about the amount of maintenance required for waterways. I’ll prepare for next week to ask the production staff further about water usage. Thank you. I also ask those who have seen it to share their opinions more
Reply #42016-07-22
It’s completely fine to use raw water; in most cases, it’s those units that require being taken offline for cleaning. It can recover within an hour if acted on quickly!
Reply #52016-07-22
What this means is that it’s actually possible to bypass it, so there’s no need to install it, right? :)
Reply #62016-07-22
Generally, items such as rotameters and Y-type filters also require an additional payment in cash
Reply #72016-07-22
Some that allow stopping at any time for a few hours can do without a secondary line. A bypass wire must be added for those that do not operate with interruptions.
Reply #82016-07-22
For certain designs that need to be modified, approval from the process team is required; only those modifications that have no impact on or only a minor impact on the manufacturing process can be implemented. Such process changes must be approved by the design institute during the construction phase, and approval for process changes is necessary after the system goes into operation.
Reply #92016-07-23
What to do if the dashboard is canceled?
Reply #102016-07-23
Remove it when the process operations permit, then rinse and inspect

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.