Participation reward: 2 Wealth. Reward for correct answer: 9 Wealth. Briefly describe the construction process for wet-grinding stone floors. The construction process for water-wetted terrazzo floors is as follows: base surface cleaning → washing with water to moisten it → setting up guide strips → applying a cement mortar leveling layer → curing → installing dividing strips → applying cement-gravel paste → curing → grinding → waxing and polishing.
Reply #22016-09-14
1. Characteristics: (1) Terrazzo floors are wear-resistant. (2) Terrazzo floors are more aesthetically pleasing and elegant. (3) Economically, terrazzo floors are cheaper than tile floors. (4) Terrazzo floors have small gaps between their components, making them less prone to cracking. 2. Scope of application: This method is suitable for floor finishing projects with medium or lower standards, especially in hospitals and schools. 3. Process Principle: The basic principle of the terrazzo floor construction method is to first level the surface with mortar, mark grid lines, and install grid strips. While applying a cement paste bond layer, the terrazzo mix is prepared and laid down; thereafter, it is rolled flat with rollers. Once it has reached a certain strength, a trial grinding is carried out. After confirming that everything is correct, the surface is ground roughly, then more finely, until it is polished. To achieve a significant effect after waxing, first scrub with oxalic acid and then apply wax for polishing. 4. Process flow and key operation points 4.1 Process flow: Base treatment → Marking the elevation with a level line → Applying the leveling mortar → Curing → Marking grid lines → Mixing the grouting material → Mixing the aggregate material → Applying a cement slurry bond layer → Spreading the terrazzo mixture → Rolling to level it → Trial grinding → Rough grinding and fine grinding → Polishing → Cleaning with oxalic acid → Waxing and finishing
Reply #32016-09-14
Base treatment → Marking horizontal lines with a level → Applying the leveling mortar → Curing → Marking grid lines → Mixing water for the grid strips → Mixing the aggregate mixture → Applying a cement slurry bond layer → Spreading the terrazzo mixture → Rolling to level it → Trial grinding → Rough grinding and fine grinding → Polishing → Cleaning with oxalic acid → Waxing and finishing
Reply #42016-09-14
The basic principle of the terrazzo floor construction process is to first level the surface with mortar, mark the grid lines, and install the grid strips. While applying a cement paste bond layer, the terrazzo mix is prepared and laid down; thereafter, it is rolled flat with a roller. Once it has reached a certain strength, a trial grinding is carried out, and after verification, rough grinding, fine grinding are performed until the surface is polished. To achieve a significant effect after waxing, first scrub with oxalic acid and then apply wax for polishing. Process flow: Base treatment → Marking the elevation with a level line → Applying the leveling mortar → Curing → Marking the grid lines → Mixing the grouting material → Mixing the stone aggregate → Applying a cement slurry bond layer → Spreading the terrazzo mixture → Rolling to level it → Trial grinding → Rough grinding and fine grinding → Polishing → Cleaning with oxalic acid → Waxing and finishing
Reply #52016-09-14
Construction process: Clean the base layer → Wash it with water to moisten it → Install guide strips → Apply a cement mortar leveling layer → Cure it → Embed dividing strips → Apply cement gravel paste → Cure it → Grind it → Wax and polish it.
Reply #62016-09-14
Base cleaning → Watering to moisten the surface → Installing guide strips → Applying a cement mortar leveling layer → Curing → Embedding partition strips → Applying cement gravel paste → Curing → Grinding → Waxing and polishing.
Reply #72016-09-14
The construction process for water-wetted terrazzo floors is as follows: base surface cleaning → washing with water to moisten it → setting up guide strips → applying a cement mortar leveling layer → curing → installing dividing strips → applying cement-gravel paste → curing → grinding → waxing and polishing.
Reply #82016-09-14
Base treatment -- Wetting with water -- Mixing of base plaster -- Marking lines for moldings and baseboards -- Applying the base plaster -- Curing of the base plaster layer -- Installing dividing strips -- Mixing lime slag -- Applying the lime slag layer -- Curing -- Polishing and pickling -- Waxing
Reply #92016-09-14
Construction techniques: (1) Substrate preparation – Check the flatness and elevation of the substrate; address any protrusions, and remove dust, debris, and oil stains. (2) Watering to moisten: The base surface should be watered and moistened the day before applying the plaster. (3) Mixing the base plaster: The mix ratio for the base plaster is 1:3 for dry-hard cement mortar used on floors, and 1:3 for plastic cement mortar used on baseboards. It is required that the mix ratio be accurate and the mixture well blended. (4) Marking the guides and skirtings: Determine the floor level based on the horizontal line at +50cm on the wall, taking into account the thickness of the finishing layer. Draw lines along the wall edges to mark the positions for applying mortar guides; the spacing between these guides is generally 1–1.5 meters. Floors with floor drains should be sloped in accordance with design requirements; generally, the slope of the edge profile along the drainage direction is 0.5%-1%. Based on the thickness of the wall plastering, squares are used at the internal and external corners, along with rulers and strings, to determine the thickness and height of the skirting boards. Guides are marked according to the thickness of the underlying plastering, with a spacing of generally 1–1.5 meters. (5) Applying base mortar: Before applying the mortar, brush a 1:0.5 cement paste on the substrate.
Reply #102016-09-14
The process for installing a wet-grouted terrazzo floor is as follows: base surface preparation – moistening with water – mixing the underlayment mortar – marking lines and setting the skirtings – applying the underlayment mortar – curing the underlayment layer – installing dividing strips – mixing the stone aggregate mortar – applying the stone aggregate mortar layer – curing – polishing and acid washing – waxing
Reply #112016-09-14
(1) Substrate preparation (2) Wetting the surface: The substrate should be wetted the day before applying the plaster to it. (3) Mixing the base plaster (4) Marking lines for joints and skirtings (5) Applying the base plaster (6) Curing the base plaster (7) Installing dividing strips (8) Applying the surface layer of gravel plaster (9) Polishing and pickling (10) Waxing

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.