HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Purging plan for chemical processing units

2016-09-14View Original

Thread Content

Could someone please share a cleaning and purging plan for chemical plant facilities after construction is completed? It’s better to be more detailed, such as the purging of pipelines and the purging of welding check valves. Thank you
Reply #22016-09-14
The purging plan essentially consists of the principles and precautions for purging, followed by a detailed description of the purging process; The purging principle is roughly as follows: Steam and the pipeline to be purged are used to remove any condensate, thereby preventing water hammer ; For the cold exchange equipment, purge one side while venting the other to avoid pressure buildup ; Remove delicate instrument valves (such as pressure and flow meters, orifice plates, mass flow meters, control valves, safety valves, etc.) to prevent weld slag from entering the valve body and damaging the valves or instruments ; The pump is connected to a bypass line to prevent damage to the mechanical seal ; For cold exchange equipment, use the bypass line first and then purge the equipment itself ; During the purging process, closely monitor the pressure at various points to prevent equipment damage caused by overpressure or backpressure resulting from condensation ; During purging, the steam flow rate should be increased gradually and slowly to prevent damage to pipeline equipment caused by sudden temperature rises ; Control the steam consumption and the pressure in the steam main to prevent low steam pressure caused by an excessive number of purge points, which would result in poor purge efficiency ; Large-diameter pipes require blasting and target cleaning for purging ; The purge control of the distillation tower regulates the steam flow to prevent the trays from being overturned ; Vent at high points, drain at low points – leave no dead corners ; Equipment that is sensitive to water (such as equipment equipped with catalysts, adsorbents, desiccants, desulfurizers, etc.) must be disconnected from the purging system to prevent steam from entering..... Friends who are familiar with this process, please add more details.
Reply #32016-09-14
This depends on the pipeline and the medium
Reply #42016-09-15
First be in charge, then just handle it; Segmented purging is used, and the next step is only taken after it is successful ; Blowing out the equipment is strictly prohibited before it is qualified ; For some sophisticated instruments, the valves need to be removed and replaced with bypasses ; Blow-down using blasting method was employed, and the target testing passed ; Ensure proper safety isolation at the discharge outlet.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.